Whether a sprinkler water supply really delivers the flow written in the calculation is known only by measurement. For this TS EN 12845+A2:2026 sets out the permanent measuring arrangements in Clause 8.5, the test procedure in Clause 8.6 and the periodic repetition in Clause 20. Source: TS EN 12845+A2:2026, Clauses 8.5 and 8.6, EN p.44-46 (TSE p.47-49).
1. Clause 8.5.1: General requirements for the measuring devices
Clause 8.5.1 (EN p.44) opens as follows: "Pressure and flow measuring devices shall be permanently provided for sprinkler systems in order to check compliance with Clause 7.3 and Clause 10, and the following shall apply:"
| Item | Requirement |
|---|---|
| a | All the devices in a test unit shall be fit for purpose and installed in accordance with the manufacturer's instructions. The manufacturer's instructions shall include the minimum lengths of straight pipe upstream and downstream of the flow measuring device and the maximum flow velocity. |
| b | The flow measuring device shall be installed in a frost proof area in a suitable position for easy access and reading. |
| c | All flow measuring devices shall have an error within ± 5 % of their maximum flow. Where the device can be affected during transport, installation or continuous use, it shall be rechecked before the test results are used to assess the available flow. |
| d | Where a calculated system is used, the capacity of the flow measuring device shall be selected so that the system demand for both the most unfavourable and the most favourable area can be measured. The device shall also have a measuring capacity of at least 140 % of the maximum demand flow (see Clause 7.3). Where the system demand is provided by more than one pump set operating in parallel, the capacity of the flow measuring device may be selected on the basis of the capacity of the largest pump; in that case the individual readings may be added provided the suction and delivery arrangement does not affect the result. |
| e | The pressure readings to be used for the pressure and flow test curve shall be taken only with an accurate test gauge (± 1.6 %). |
| f | At least three (3) pressure and flow readings shall be taken to establish a test curve. In addition, a pressure reading with no flow, that is the static pressure, shall be taken. |
Where the device is installed depends on the type of water supply: where the water supply is an automatic pump set or sets, the flow measuring device is installed in the pump room (see Clause 8.5.2) and in that case Clause 8.5.1 does not apply. Where the water supply is not an automatic pump, the device is installed at the control valve sets (see Clause 8.5.3).
2. Clause 8.5.2: In the pump room
Clause 8.5.2 (EN p.45):
- A permanently installed flow measuring device shall be provided and shall be able to check each water supply or pump set. Where the test apparatus is not permanently fitted, it shall be available on site at all times.
- Pressure gauges shall be positioned upstream and downstream of the pump, on a straight length of pipe.
- Where the system demand is provided by more than one pump operating in parallel, the capacity of the flow measuring device may be selected on the basis of the capacity of the largest pump; in that case the individual readings may be added provided the suction and delivery arrangement does not affect the result.
3. Clause 8.5.3: At the control valve sets
Where the water supply is not an automatic pump set or sets (Clause 8.5.3, EN p.45):
- A flow measuring device permanently available on site (fixed or portable) shall be provided and shall be able to check each water supply.
- Where two or more control valve sets are installed together, it is sufficient to install the device only at the hydraulically most remote set; where the installations belong to different hazard classes, it is installed at the control valve set requiring the highest water flow.
- In all cases appropriate allowance shall be made for the pressure losses between the water supply and the control valve set or sets, using the calculation methods specified in Clause 13.2.
- Provision shall be made for the disposal of the test water.
- On dry or alternate control valve sets (main or subsidiary), an additional flow test valve arrangement with an unspecified flow loss characteristic may be fitted below the control valve set and downstream of the main stop valve, in order to facilitate an informal test of the supply pressure. These flow test valves and pipework shall be of 40 mm nominal diameter on LH installations and 50 mm on other installations.
The 40 and 50 mm values in the last sentence apply only to this additional flow test valve; the general drain valve diameters are in Table 39.
4. Clause 8.6: Testing of the water supply
8.6.1 General (EN p.45):
The test arrangement specified in Clause 8.5.2 shall be used. Each supply to the installation shall be tested independently with all other supplies isolated. In both pre-calculated and fully calculated installations the water supply shall be tested at not less than the maximum demand flow of the installation.
8.6.2 Storage tank and pressure tank supplies (EN p.45-46): the stop valves controlling the flow from the water supply to the installation shall be fully opened. The operation of the automatic pump set shall be checked by reducing the system pressure. The flow shall be verified in accordance with Clause 7. The supply pressure measured at the 'C' gauge shall be verified as being at least the relevant value specified in Clause 7.
8.6.3 Town main, booster pump, elevated private reservoir and gravity tank supplies (EN p.46): the stop valves controlling the flow from the supply to the installation shall be fully opened. The operation of the automatic pump set shall be checked by reducing the system pressure. The drain and test valve shall be adjusted to give the flow specified in Clause 7. When the flow has stabilized, the supply pressure measured at the 'C' gauge shall be verified as being at least the relevant value in Clause 7.
For a boosted town main, Clause 10.7.4 (EN p.63) defines a further test: a test is carried out to demonstrate that the unboosted supply provides the maximum demand flow plus 20 % at a pressure of at least 0.5 bar measured at the pump inlet. This test is carried out at the time of maximum demand on the main.
5. Pressure gauges and test valves
Pressure gauges (Clause 15.7, EN p.109)
- The gauge scale divisions shall not exceed the following: 0.2 bar where the maximum scale value is equal to or less than 10 bar, and 0.5 bar where it is greater than 10 bar. The maximum scale value should be of the order of 150 % of the maximum pressure (15.7.1).
- A pressure gauge (the 'A' gauge) is fitted at each town main connection, between the supply pipe stop valve and the non-return valve (15.7.2).
- A damped pressure gauge is fitted to each pump set supply, immediately downstream of the outlet non-return valve and upstream of the outlet stop valve where one is provided (15.7.2).
- Three positions apply to the control valve set (15.7.3): immediately upstream of each control valve set (the 'B' gauge); immediately downstream of it (the 'C' gauge); and immediately downstream of each alternate or dry subsidiary control valve set but upstream of any stop valve. The 'B' gauge on dry alarm valves shall have an indicator showing the maximum pressure reached.
- Provision is made for each gauge to be removed without interrupting the water or air supply to the installation (15.7.4).
Test valves (Clause 15.5, EN p.108-109)
15.5.1 Alarm and pump set starting test valves: test valves of 15 mm shall be suitably fitted to test the following:
- a) the hydraulic alarm and the electrical alarm pressure switch where provided, by drawing water from immediately downstream of the wet alarm valve and of any main stop valve downstream of it, or from downstream of an alternate alarm valve;
- b) the hydraulic alarm and the electrical alarm pressure switch where provided, by drawing water from downstream of the main water supply stop valve and upstream of the following: an alternate alarm valve, a dry pipe alarm valve, a pre-action alarm valve;
- c) any water flow alarm switch installed downstream of the control valve set, by drawing water from downstream of the water flow alarm;
- d) the automatic pump set starting device;
- e) any pump or pressure tank room local sprinkler alarm flow switch installed upstream of the control valve set.
15.5.2 Remote test valves: a test arrangement shall be provided comprising a test valve connected at the hydraulically most remote position of a distribution pipe giving a flow equivalent to the discharge of a single sprinkler, together with the associated fittings and pipework.
Drain valves (Clause 15.4, Table 39, EN p.107-108)
Drain valves are fitted at the following points: a) immediately downstream of the control valve set or of any stop valve downstream of it; b) immediately downstream of any subsidiary alarm valve; c) immediately downstream of any subsidiary stop valve; d) between a dry pipe or subsidiary control valve set and any subsidiary stop valve installed for testing purposes; e) on every pipe that cannot be drained from another drain valve, excluding drop pipes to single sprinklers in a wet installation. The valves are fitted at the lower end of the pipework; the outlet is not more than 3 m above floor level and is provided with a suitable plug.
| Valve draining principally | Minimum valve and pipe diameter (mm) |
|---|---|
| LH installation | 40 |
| OH or HHP or HHS installation | 50 |
| Subsidiary installation | 50 |
| A zone | 50 |
| Trapped distribution pipes, diameter ≤ 80 mm | 25 |
| Trapped distribution pipes, diameter > 80 mm | 40 |
| Trapped range pipes | 25 |
| Trapped pipework between a dry or subsidiary alarm valve and a subsidiary stop valve installed for testing purposes | 15 |
Source: Table 39, Clause 15.4, EN p.108 (TSE p.111).
6. Commissioning tests (Clause 19)
| Test | Requirement | Source |
|---|---|---|
| Dry pipe installation, pneumatic | A pressure of at least 2.5 bar for at least 24 hours; any leakage causing a pressure loss of more than 0.15 bar in 24 hours is rectified | Clause 19.1.1.1, EN p.117 |
| All pipework, hydrostatic | For at least 2 hours at a pressure of at least 15 bar, or 1.5 times the maximum pressure to which the system will be subjected, whichever is greater, both measured at the installation control valves | Clause 19.1.1.2, EN p.117 |
| Equipment | The system is tested once as specified in Clauses 20.2.2 and 20.3.2 (that is, the weekly and quarterly routine tests) and any faults found are rectified | Clause 19.1.2, EN p.117 |
| Water supplies | Tested once as specified in Clause 8.6; diesel engine driven pumps are tested in accordance with Clause 20.2.2.5 | Clause 19.1.3, EN p.117 |
Clause 19.1.1.2 also warns that no system component shall be subjected to a pressure higher than that recommended by the supplier. Clause 19.2 (EN p.118) covers the completion certificate and the documentation: the installer shall give the user a completion certificate stating that the system complies with all the relevant requirements of the standard or detailing the deviations, together with a complete set of operating instructions and the "as-built" design documents.
7. Periodic tests
| Interval | Test | Source |
|---|---|---|
| Weekly (≤ 7 days) | All water and air pressure gauge readings are checked and recorded; in dry, alternate and pre-action installations the pipe pressure shall not fall by more than 1.0 bar per week. All water levels and the correct position of all main stop valves are checked | Clauses 20.2.2.1, 20.2.2.2, EN p.119 |
| Weekly | Every water motor alarm is sounded for at least 30 seconds | Clause 20.2.2.3, EN p.119 |
| Weekly | Automatic pump set starting test: on diesels the fuel and oil levels; simulation of automatic operation by reducing the water pressure on the starting device; checking and recording of the starting pressure when the pump starts; on diesels the oil pressure and the cooling water flow in open circuit cooling | Clause 20.2.2.4, EN p.119 |
| Quarterly (≤ 13 weeks) | Each water supply is tested with each control valve set in the system; where fitted, the pump or pumps shall start automatically and the supply pressure at the relevant flow shall not be less than the appropriate value in accordance with Clause 10 (recognizing the modifications required by 20.3.2.2) | Clause 20.3.2.5, EN p.121 |
| Quarterly | All stop valves controlling the flow of water to the sprinklers are operated to ensure that they are in working order and securely refixed in the correct mode. This covers those at all water supplies, at the alarm valve or valves and all zone or other subsidiary stop valves | Clause 20.3.2.7, EN p.121 |
| Quarterly | The flow alarms (flow switches and/or pressure switches) are checked for correct operation | Clause 20.3.2.8, EN p.121 |
| Annually (≤ 12 months) | Each water supply pump set is tested at the full load condition by means of the test line connection coupled to the delivery branch downstream of the pump set outlet non-return valve, and shall give the pressure and flow values stated on the nameplate. Appropriate allowances are made for pressure losses in the supply pipe and valves between the source and each control valve set | Clause 20.3.4.2.1, EN p.122 |
| Annually | Where no pump is installed: each water supply is tested at the full load condition by means of the test line connection coupled to the water supply upstream of the control valve set, and shall meet the required flow and pressure values | Clause 20.3.4.2.2, EN p.122 |
| Annually | The diesel failed-to-start alarm is tested; immediately after the test the engine is started using the manual starting system | Clause 20.3.4.3, EN p.122 |
| Annually | The float valves on the water storage tanks are checked | Clause 20.3.4.4, EN p.122 |
| Annually | The pump set suction strainers, settling chamber and their screens are inspected and cleaned as necessary | Clause 20.3.4.5, EN p.122 |
| Annually | The system is periodically inspected by a qualified person (see Annex Q); the inspection report assesses whether the system complies with the standard with regard to maintenance, operation and adequacy for the risk, and a list of deviations is issued | Clause 21, EN p.123 |
The recording of all inspections is subject to Clause 20.3.1.2 (EN p.120): "A signed and dated inspection report shall be given to the user; the report shall include information on any correction made or required and details of any external factors (for example weather conditions) which may have affected the results."
8. Summary of the test sequence
- Verification of the arrangement: position and capacity of the flow meter (± 5 %, ≥ 140 %), class of the pressure gauge (± 1.6 %), positions of the upstream and downstream gauges, arrangement for disposal of the test water.
- Isolation: all supplies other than the one to be tested are isolated (Clause 8.6.1).
- Static reading: the pressure is read with no flow (Clause 8.5.1 f).
- At least three P/Q points: at least three pressure and flow readings are taken for the test curve (Clause 8.5.1 f).
- Verification at the maximum demand flow: the supply is tested at not less than the maximum demand flow of the installation (Clause 8.6.1); the pressure at the 'C' gauge shall not be less than the value in Clause 7 (Clauses 8.6.2 and 8.6.3).
- Automatic start: the starting of the pump set is checked by reducing the system pressure (Clauses 8.6.2 and 8.6.3).
- Record: a signed and dated report is issued (Clause 20.3.1.2).
Frequently Asked Questions
What accuracy and capacity are required of the flow measuring device?
TS EN 12845+A2:2026 Clause 8.5.1 c) (EN p.44): all flow measuring devices shall have an error within ± 5 % of their maximum flow. Clause 8.5.1 d): where a calculated system is used, the capacity of the device is selected so that the system demand of both the most unfavourable and the most favourable area can be measured, and the device shall also have a measuring capacity of at least 140 % of the maximum demand flow.
How many points are read for the test curve?
Clause 8.5.1 f) (EN p.45): at least three pressure and flow readings shall be taken to establish a test curve. In addition, a pressure reading with no flow, that is the static pressure, shall be taken. Under Clause 8.5.1 e), the pressure readings to be used for the pressure and flow test curve shall be taken only with an accurate test gauge (± 1.6 %).
How are the water supplies tested?
Clause 8.6.1 (EN p.45): the test arrangement specified in Clause 8.5.2 is used. Each supply to the installation shall be tested independently with all other supplies isolated. In both pre-calculated and fully calculated installations the water supply is tested at not less than the maximum demand flow of the installation.
How is the annual full load pump test carried out?
Clause 20.3.4.2.1 (EN p.122): each water supply pump set in the installation is tested at the full load condition by means of the test line connection coupled to the pump set delivery branch downstream of the pump set outlet non-return valve, and shall give the pressure and flow values stated on the nameplate. Appropriate allowances are made for pressure losses in the supply pipe and valves between the source and each control valve set.
What are the drain valve diameters?
Table 39 (Clause 15.4, EN p.108): LH installation 40 mm; OH, HHP or HHS installation 50 mm; subsidiary installation 50 mm; a zone 50 mm; trapped distribution pipes 25 mm where the diameter is ≤ 80 mm and 40 mm where it is > 80 mm; trapped range pipes 25 mm; trapped pipework between a dry or subsidiary alarm valve and a subsidiary stop valve installed for testing purposes 15 mm.
What is done in the weekly pump starting test?
Clause 20.2.2.4 (EN p.119): on diesel engines the fuel and engine lubricating oil levels are checked; the automatic starting condition is simulated by reducing the water pressure on the starting device; the starting pressure is checked and recorded when the pump set starts; on diesel pumps the oil pressure and the cooling water flow in open circuit cooling systems are checked. Clause 20.2.2.1 requires this routine at intervals of not more than 7 days.
References
- TS EN 12845+A2:2026 Clause 8.5.1 Test arrangement devices - general (EN p.44-45 / TSE p.47-48)
- TS EN 12845+A2:2026 Clause 8.5.2 In the pump room (EN p.45 / TSE p.48)
- TS EN 12845+A2:2026 Clause 8.5.3 At the control valve sets (EN p.45 / TSE p.48)
- TS EN 12845+A2:2026 Clauses 8.6.1, 8.6.2, 8.6.3 Testing of the water supply (EN p.45-46 / TSE p.48-49)
- TS EN 12845+A2:2026 Clause 10.7.4 Boosted town main pressure and water capacity (EN p.63 / TSE p.66)
- TS EN 12845+A2:2026 Clause 15.4, Table 39 Drain valves (EN p.107-108 / TSE p.110-111)
- TS EN 12845+A2:2026 Clauses 15.5.1, 15.5.2 Test valves (EN p.108-109 / TSE p.111-112)
- TS EN 12845+A2:2026 Clauses 15.7.1-15.7.4 Pressure gauges (EN p.109-110 / TSE p.112-113)
- TS EN 12845+A2:2026 Clauses 19.1.1.1-19.1.3, 19.2 Commissioning (EN p.117-118 / TSE p.120-121)
- TS EN 12845+A2:2026 Clauses 20.2.2.1-20.2.2.4 Weekly routine (EN p.119 / TSE p.122)
- TS EN 12845+A2:2026 Clause 20.3.1.2 Records (EN p.120 / TSE p.123)
- TS EN 12845+A2:2026 Clauses 20.3.2.5, 20.3.2.7, 20.3.2.8 Quarterly routine (EN p.121 / TSE p.124)
- TS EN 12845+A2:2026 Clauses 20.3.4.2.1, 20.3.4.2.2, 20.3.4.3, 20.3.4.4, 20.3.4.5 Annual routine (EN p.122 / TSE p.125)
- TS EN 12845+A2:2026 Clause 21 Periodic system inspection (EN p.123 / TSE p.126)

SprinkCalc — Fire Sprinkler Design Across Three Standards
SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.
Download SprinkCalc on the App Store
MEP Calc — 86+ Engineering Calculators
MEP Calc bundles 86+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.
Download MEP Calc on the App StoreTS EN 12845+A2:2026 (EN 12845:2015+A2:2026) Fixed firefighting systems — Automatic sprinkler systems — Design, installation and maintenance; TS EN 12845-2:2025 (EN 12845-2:2024) ESFR and CMSA sprinkler systems. Every figure in this article is taken from the published standard text; clause, table and page references are listed under References. General information only, not a substitute for the standard or for a design review.