Short answer: FM DS 8-9 covers in-rack sprinklers (IRAS) as the supplement to ceiling sprinklers in Section 2.3.4. Figure 3 decides whether they are needed; the sprinkler is 70 °C, quick-response and at least K8.0 (K115) when the design flow exceeds 115 L/min; face sprinklers sit within 450 mm of the rack face and the deflector at least 150 mm above the top of storage. The horizontal layout is either at every other transverse flue intersection (IRAS(EO)) or at every intersection (IRAS(E)); vertical increments are 7.5 / 6.0 / 4.5 / 3.0 m by commodity (Figure 15). The hydraulic design comes from Table 12 (Class 1-3: 6 or 10 sprinklers @ 85 L/min; Class 4 and plastics: 8 or 14 sprinklers @ 115 L/min) and the ceiling design from Table 13. "CMSA" is not a separate table in DS 8-9; the standard-response columns are that family.

This article has been rewritten from the text of FM Global DS 8-9 (March 2010, Interim Revision April 2026); statements in the previous version such as "K115-K240 CMSA ceiling, K11.2 in-rack at 0.5-1 bar, one level every 3 m" are not in the data sheet and have been removed. Every value below is given with its DS 8-9 section, table or figure number.

1. What does "CMSA" mean in DS 8-9?

The revision history (Appendix B) explains that sprinklers are categorised as Suppression Mode (formerly ESFR), Control Mode Specific Application (formerly Large-Drop) and Control Mode Density Area (formerly Standard), but that the protection tables were reformatted by sprinkler type. In the current text every ceiling design sits in one table format: in Tables 2 to 11 the standard-response pendent (K11.2, K14.0, K19.6, K25.2), standard-response upright (K11.2, K16.8, K25.2) and 280 °F dry-system columns represent the "control mode" side, while the quick-response pendent and upright columns represent the "suppression mode" side. For example, Table 7 (Class 1-3, open-frame racks) gives, at a 9.0 m ceiling, standard-response pendent K11.2 18 @ 50 psi (3.5 bar), K14.0 18 @ 32 psi (2.2 bar), K19.6 9 @ 16 psi (1.1 bar) and K25.2 9 @ 10 psi (0.7 bar); in the same row quick-response pendent K25.2 reads 9 @ 20 psi (1.4 bar). The ceiling side is covered in the Storage sprinkler decision matrix; this article covers the in-rack side.

2. When are in-rack sprinklers needed? (Section 2.3.4.2, Figure 3)

Rack storage is protected either by a ceiling-only system or by a combination of ceiling and in-rack sprinklers (2.3.4.1). The need depends on commodity hazard, ceiling height, available water supply, the presence of solid shelves or open-top containers, and the width and location of flue spaces. The questions of Figure 3, in order:

  1. Does the rack arrangement qualify as open-frame per Section 2.2.3.2?
  2. Is there a ceiling-only option in the applicable table (Tables 7 to 11, 14a, 14b or 17b), and can the available water supply meet its flow and pressure demand?
  3. Will open-top containers be stored in the racks? (Are in-rack sprinklers recommended in Section 2.2.4?)
  4. Does the rack qualify as a rack with solid shelves greater than 64 ft² (6.0 m²)?
  5. Is the commodity Class 1-4 or cartoned plastics; does the storage height exceed 15 ft (4.5 m) or 10 ft (3.0 m); is the maximum ceiling over 30 ft (9.0 m)?

Every negative branch ends in "in-rack sprinklers will be needed". When they are needed, the six steps of Section 2.3.4.1.4 follow: horizontal arrangement (2.3.4.6), vertical increments (2.3.4.7), in-rack hydraulic design (2.3.4.8.1), ceiling design when supplemented by in-rack sprinklers (2.3.4.8.2), sprinklers per branch line for the ceiling system (Table 1) and hose demand and duration for the combined system (2.3.5).

3. Open-frame definition and flue spaces (Section 2.2.3.2)

Rack classes: single-row when the depth does not exceed 6 ft (1.8 m) and a minimum 4 ft (1.2 m) aisle separates it from adjacent racks; double-row when the depth exceeds 1.8 m but not 12 ft (3.7 m) with minimum 1.2 m aisles; otherwise multiple-row (2.2.3.2.1.1-3). Racks with grated, mesh or slatted shelves count as open-frame when the openings are at least 70 % of the shelf area and flue spaces are adequate; solid shelves not exceeding 20 ft² (1.9 m²) also count as open-frame (2.2.3.2.1.4-6). Rolled commodities are arranged so they cannot bulge into transverse flues (2.2.3.2.1.7). Racks not meeting these guidelines are treated as racks with solid shelves; the solid shelf dimension is defined by the surrounding flues: net 150 mm transverse flues (75 mm at rack uprights), net 75 mm longitudinal flues in double-row racks and net 150 mm longitudinal flues in multiple-row racks (2.2.3.2.1.9).

Rack typeAdequate flue space optionsSource
Single-rowNet 75 mm transverse flues at most every 1.4 m (Figure 2a); or net 150 mm transverse flues every 2.7 m (Figure 2b); with misaligned flues, vertically aligned net 150 mm flues every 1.4 m (Figure 2c)2.2.3.2.2.2
Double-rowNet 75 mm longitudinal + net 75 mm transverse flues every 1.4 m (Figure 2d); or 75 mm longitudinal + 150 mm transverse flues every 2.7 m (Figure 2e); longitudinal flue under 75 mm: aligned 150 mm transverse flues every 1.5 m (Figure 2f); misaligned transverse flues: 75 mm longitudinal + aligned 150 mm transverse flues every 1.4 m (Figure 2g)2.2.3.2.3.2
Multiple-rowNet 150 mm longitudinal flues every 1.5 m + net 150 mm transverse flues every 1.5 m (Figure 2h); or depth limited to 20 ft (6.1 m) by minimum 8 ft (2.4 m) aisles with 150 mm transverse flues every 1.5 m (Figure 2i)2.2.3.2.4.2

Where double-row and multiple-row racks are protected by in-rack sprinklers, flue spaces are not required for the tier directly above the sprinklers (2.2.3.2.3.4, 2.2.3.2.4.4).

4. In-rack sprinkler selection and position (Sections 2.3.4.3-2.3.4.5)

5. Horizontal arrangements: IRAS(EO) and IRAS(E) (Section 2.3.4.6)

There are two basic arrangements: IRAS(EO), sprinklers at every other transverse flue intersection between pallet loads; IRAS(E), sprinklers at every transverse flue intersection (2.3.4.6.1.1). Which one is acceptable depends on rack type, commodity, open-top containers, maximum ceiling height, whether the 150 mm vertical clearance is provided and whether horizontal barriers are installed (2.3.4.6.1.2); the decision comes from the flowcharts in Figure 5 (single-row ≤ 0.9 m), 5a (single-row > 0.9 m), 6 (double-row ≤ 2.7 m), 6a (double-row > 2.7 m) and 7 (multiple-row). The figures show pallet loads as nominal 20 ft² (2.0 m²) squares.

6. Vertical increments (Section 2.3.4.7, Figure 15)

ConditionIn-rack vertical increment
Open-top containersPer Section 2.2.4
Solid shelves > 64 ft² (6.0 m²)Below every such shelf; maximum 10 ft (3.0 m) of storage above the top level
Solid shelves > 20 ft² (2.0 m²)Not exceeding 15 ft (4.5 m) where the highest hazard is below cartoned plastics; otherwise 10 ft (3.0 m)
Open-frame, highest hazard below Class 3Not exceeding 25 ft (7.5 m)
Open-frame, below cartoned unexpanded plasticsNot exceeding 20 ft (6.0 m)
Open-frame, below cartoned expanded plasticsNot exceeding 15 ft (4.5 m)
Open-frame, uncartoned plasticsNot exceeding 10 ft (3.0 m)

The increments apply to levels below the top of storage as well as to any level installed above it (2.3.4.7.2). Where the first tier rests on a horizontal support rather than the floor, the distance may be measured from the underside of the first-tier pallet load (2.3.4.7.3).

7. Hydraulic design: Table 12 and Table 13 (Section 2.3.4.8)

CommodityStorage above top IRAS levelInstalled IRAS levelsSprinklers in designMinimum flow per sprinkler
Class 1-3≤ 10 ft (3.0 m)1622 gpm (85 L/min)
2 or more10 (5 on 2 levels)
Class 4 and plastics≤ 10 ft (3.0 m)1830 gpm (115 L/min)
2 or more14 (7 on 2 levels)

Minimum operating pressure 7 psi (0.5 bar) (2.3.4.8.1.3); the in-rack demand is hydraulically balanced with the ceiling demand at the point of connection (2.3.4.8.1.2). The ceiling system is designed from Table 13, which states, by commodity, IRAS arrangement (EO/E), storage height above the top IRAS level (1.5 or 3.0 m) and clearance between the top of storage and the ceiling, which protection table (7, 8 or 10) and which ceiling height row to use. Examples: Class 1-3, IRAS(EO), 1.5 m of storage above the top level and 1.5 m clearance → Table 7, 10 ft (3.0 m) row; clearance up to 6.0 m → Table 7, 20 ft (6.0 m) row. Class 4 and cartoned plastics use the 10, 15 or 20 ft rows of Table 8; uncartoned plastics the 15-20 ft rows of Table 8 or 10. Where the clearance exceeds 6.0 m, Section 2.3.3.7.3 applies. With horizontal barriers or sprinklers under solid shelves, the IRAS(E) row is used (2.3.4.8.2.2).

8. Special applications (Section 2.3.6)

The retrofit design for uncartoned plastics in Section 2.3.6.7 (minimum K22.4 quick-response pendent face sprinklers, 455 L/min, Table 17) is described in the plastic storage article.

Field note: the three most common in-rack non-conformities concern flue spaces: transverse flues closed by carton overhang, longitudinal flues shrinking below 75 mm, and sprinklers hidden behind uprights. DS 8-9 defines all of them by dimension (2.2.3.2, 2.3.4.5.5) and asks for a physical means to keep flues open where they cannot be maintained (2.2.3.2.1.7). The loss history section (3.2) calls in-rack sprinklers used with ceiling sprinklers "overwhelmingly successful"; failures always come from installation deficiencies: inadequate water supply, closed valves, obstructed piping, missing sprinklers.

Quick checklist

Frequently Asked Questions

When does FM DS 8-9 require in-rack sprinklers?

Per Section 2.3.4.2 and Figure 3 the need depends on commodity hazard, ceiling height, available water supply, solid shelves or open-top containers, and flue spaces. The main questions: are the racks open-frame, is there a ceiling-only option in the tables and can the water supply meet it, are open-top containers present, do solid shelves exceed 6.0 m², does storage exceed 3.0 m or 4.5 m.

Which K-factor and temperature rating are used for in-rack sprinklers?

Section 2.3.4.3: 160 °F (70 °C), quick-response FM Approved in-rack sprinklers; minimum K8.0 (K115) when the design flow exceeds 115 L/min. Water shields when two levels are in the design; not needed with horizontal barriers or solid shelves.

How many sprinklers and what flow are used in the in-rack hydraulic design?

Table 12: Class 1-3, 6 sprinklers for one level or 10 (5 on 2 levels) for two or more, 85 L/min; Class 4 and plastics, 8 or 14 sprinklers (7 on 2 levels), 115 L/min. Storage above the top level does not exceed 3.0 m, minimum pressure 0.5 bar, hydraulic balance with the ceiling.

What is the maximum vertical distance between in-rack sprinkler levels?

Figure 15: with solid shelves over 6.0 m², below every shelf and 3.0 m of storage above the top. In open-frame racks by hazard: 7.5 m (below Class 3), 6.0 m (below cartoned unexpanded plastics), 4.5 m (below cartoned expanded plastics), 3.0 m (uncartoned plastics). With solid shelves over 2.0 m², 4.5 or 3.0 m.

What are the minimum flue space dimensions?

Section 2.2.3.2: single-row racks 75 mm transverse flues every 1.4 m or 150 mm every 2.7 m; double-row racks 75 mm longitudinal + 75 mm transverse every 1.4 m or 150 mm transverse every 2.7 m, and 150 mm transverse every 1.5 m where the longitudinal flue is under 75 mm; multiple-row racks 150 mm longitudinal and transverse flues every 1.5 m. No flue is required for the tier directly above in-rack sprinklers.

References

Sources & Disclaimer

Values are transcribed from the FM Global data sheet above with section, table and figure numbers. This article is for general information; the design must be based on the FM Approval listing of the selected product and the current data sheet text, carried out by a qualified engineer and accepted by the insurer.

FS

Fatih Selvi

Mechanical engineer and software developer. 16+ years in mechanical and fire protection systems. NFPA 13/14/20/25 and Turkish fire code specialist.