Skip to content
Pumps

EN 12845 fire pump suction and start check

Enter the suction condition, maximum demand flow, suction pipe size, NPSH values and closed-valve pressure. The tool checks the suction and starting rules of BS EN 12845+A2 Section 10 one by one.

BS EN 12845+A2Clause 10.6Clause 10.7.5Table 15

This tool is for preliminary sizing and checking; confirm the final design against the edition of the standard in force and the authority having jurisdiction.

38 more calculators ↓

What does this tool check?

The pump suction and starting rules of BS EN 12845+A2:2026 Section 10: suction pipe size and velocity, pump centre line position relative to the water level, NPSH margin, number of pumps, pressure-switch start pressures and the automatic priming tank under suction lift. It does not select a pump or check a pump curve.

What changed with A2: water supplies consisting of pumps conform to EN 17451 (Clause 10.1), and pump set documentation is provided in accordance with that standard (Clause 4.4.4.4). The pump set performance characteristics remain in Clause 10.7 of BS EN 12845+A2: in pre-calculated LH and OH systems a pump taking water from a storage tank conforms to Table 16 (Clause 10.7.1), in pre-calculated HHP and HHS systems with no in-rack sprinklers the nominal flow and pressure conform to Clause 7.3.2 (Clause 10.7.2), and in calculated systems the pump set is chosen to meet the pressure and flow demand of the sprinkler system (Clause 10.7.3). The tool does not check the pump curve.

Positive head or suction lift? (10.6.1)

Wherever possible, horizontal centrifugal pump sets are installed with a positive suction head. Both conditions apply together:

If this is not feasible, the pump may be installed under suction lift conditions or vertical turbine pumps may be used. Suction lift and submersible pump arrangements are avoided unless a positive suction head is not practicable.

Suction pipe (10.6.2.2 and 10.6.2.3)

ConditionMinimum diameterMaximum velocityFurther rule
Positive head65 mm1.8 m/sSuction pipes may be interconnected only with stop valves so that each pump set keeps running when the other is removed
Suction lift80 mm1.5 m/sLow water level to pump centre line ≤ 3.2 m; suction pipes not interconnected; foot valve at the lowest point

The velocity is taken with the pump operating at maximum demand flow: v = Q / (π · d² / 4) The tool uses an approximate bore for steel pipe (sch 40) for each DN; the real bore depends on the pipe standard.

NPSH margin (10.6.2.1)

The suction piping, with all valves and fittings, is designed so that the available NPSH at the pump inlet (calculated at the maximum anticipated water temperature) exceeds the required NPSH by at least 1 m at the maximum pump set flow. Use the NPSH calculator to work out NPSHa from altitude, temperature and friction loss; NPSHr comes from the pump manufacturer.

Number of pumps (10.2)

Pressure switches (10.7.5)

Two pressure switches start each pump set; the sensing pipe is at least 15 mm and either switch starts the pump. The first pump starts before the trunk main pressure falls to 0.8 p; where two pump sets are installed, the second starts before it falls to 0.6 p, p being the closed-valve pressure. Once started, the pump runs until stopped manually.

Automatic priming (10.6.2.4, Table 15)

Hazard classPriming tank at leastPriming pipe at least
LH100 L25 mm
OH, HHP and HHS500 L50 mm

If the water in the priming tank falls to 2/3 of its normal level, the pump starts, or an alarm is sent to a permanently attended location.

Frequently Asked Questions

What is the velocity limit in the suction pipe?

Under BS EN 12845+A2, with the pump at maximum demand flow, 1.8 m/s is not exceeded under positive head (Clause 10.6.2.2) and 1.5 m/s under suction lift (Clause 10.6.2.3). The minimum diameter is 65 mm under positive head and 80 mm under suction lift.

What counts as a positive suction head?

Clause 10.6.1: at least two thirds of the effective capacity of the suction tank is above the pump centre line and the centre line is no more than 2 m above the low water level. If this is not feasible, the pump may be installed under suction lift conditions or vertical turbine pumps may be used; under suction lift the low water level to pump centre line distance is at most 3.2 m (Clause 10.6.2.3).

At what pressure must the pump start?

Clause 10.7.5: the first pump starts before the trunk main pressure falls to 0.8 p and, where two pump sets are installed, the second before it falls to 0.6 p, p being the closed-valve pressure. Each pump set has two pressure switches and runs until stopped manually.

Does the tool check the pump curve?

No. BS EN 12845+A2 requires water supplies consisting of pumps to conform to EN 17451 (Clause 10.1), while the pump set performance characteristics remain in Clause 10.7: Table 16 for pre-calculated LH and OH (Clause 10.7.1), Clause 7.3.2 for pre-calculated HHP and HHS with no in-rack sprinklers (Clause 10.7.2), and the pressure and flow demand of the sprinkler system for calculated systems (Clause 10.7.3). This tool checks only the suction and starting rules; check the pump curve separately against Clause 10.7.

MEP Calc — 110+ Engineering Calculators

MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store

SprinkCalc — Fire Sprinkler Design in Three Standards

Run these calculations on site, offline and with PDF reports: NFPA 13, FM Global and BS EN 12845 in one iOS app.

Get SprinkCalc on the App Store

Related content

Other fire protection calculators

All calculators →